Math
A machine P can paint one lakh books in 8 hours; machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines started operating at 9 A. M. while machine P is stopped at 11 A. M. and the reamaining two machines completed the work. Approximately at what time will the work (to print one lakh books) be finished?
A) 11:30 A. M
B) 12:00 noon
C) 12:30 P. M.
D) 1:00 P. M.