A can complete a piece of work in 12 days, A, B and C can complete the work in 6 days. Efficiency of B is 0.5 times the efficiency of A. In how many days C can complete the work alone?
একটি অপশন বেছে নিন
একটি অপশন বেছে নিন
আগের প্রশ্ন
A train can cross another train of equal length coming form the opposite direction with th...
পরের প্রশ্ন
A shopkeeper sold and item at 20% profit and another item at 10% loss. If the cost price o...
A shopkeeper sold and item at 20% profit and another item at 10% loss. If the cost price of both the items is...
উত্তর ও ব্যাখ্যা দেখুন Math8 males and 6 females can do a piece of work in 5 days, 5 males and 6 females can complete the same work in 7...
উত্তর ও ব্যাখ্যা দেখুন MathA is 30% more efficient than E How much time will they , working together , take to complete a job which A alo...
উত্তর ও ব্যাখ্যা দেখুন MathThe area of lawn is 460 . If the length is 15 percent more than the breadth of the rectangular field What is t...
উত্তর ও ব্যাখ্যা দেখুন MathA boat can travel form point A to point B and return back to point a in 9 hours. Speed of the boat in still wa...
উত্তর ও ব্যাখ্যা দেখুন MathA 10% monthly salary increase resulted in a TK. 9000 per year increase in salary for an employee. What was his...
উত্তর ও ব্যাখ্যা দেখুনএটি Math বিষয়ের একটি গুরুত্বপূর্ণ MCQ প্রশ্ন, যা বিসিএস, ব্যাংক জব, প্রাইমারি শিক্ষক নিয়োগ ও অন্যান্য সরকারি-বেসরকারি চাকরির পরীক্ষায় বারবার আসার সম্ভাবনা থাকে। প্রশ্নটির সঠিক উত্তর A) 24 days।
JobGenius BD™-তে আপনি Math বিষয়ের আরও অনেক MCQ ব্যাখ্যাসহ প্র্যাকটিস করতে পারবেন, দুর্বল জায়গা চিহ্নিত করে নিয়মিত প্রস্তুতি নিতে পারবেন।
সঠিক উত্তর: A) 24 days।
প্রশ্নটি Math বিষয়ের অন্তর্ভুক্ত।
জব প্রিপারেশন পেজ থেকে বিষয়ভিত্তিক সব MCQ প্র্যাকটিস করতে পারবেন।
এখানে ক্লিক করে ভুলটি জানান, আমরা যাচাই করে সংশোধন করব।